Facility Qualification Protocol

Facility Qualification is a process in which it is evaluated and documented whether or not a suitable facility is used to produce the products. Facility Qualification covers inspecting the production areas to check if rooms are appropriately sized; walls are of proper construction and finish to facilitate easy cleaning; there is sufficient lighting; facilities for proper ventilation and utilities are available; and sufficient drainage is in place. The latest building plans are annotated to record discrepancies.


Facility Qualification can consist of the following information:
  1. Construction Materials: Determination of construction materials installed in rooms for walls, ceilings, and flooring. Determination of surface cleanability and acceptability for use in areas rated for particulates. Doors and windows must be in correct construction and in correct location.
  2. Lighting Levels: Evaluation of lighting levels in the workplace to make sure it is sufficient for operations conducted.
  3. Drainage: Sizing and inspection of floor drains for determining size and appropriate use of the drains in all processing areas. Inspect the system to ensure correct installation and compliance with design requirements.
  4. Drain Air Breaks: System identification and inspection to ensure sufficient air breaks are present in an effort to abate back-siphonage.
  5. Utilities: Documentation of identification and inspection of utilities (such as purified water, compressed gases and air, and clean steam) necessary for use by the process, and listed for each room to ensure correct installation and compliance to design requirements. Air supply and return grilles and diffusers are also documented.

Facility Qualification Protocol

TABLE OF CONTENT

Sr. No.

Title of Sections

1.0

Pre-approval Protocol

2.0

Objective

3.0

Scope

4.0

Reason for Facility Qualification

5.0

Responsibility

6.0

USER REQUIREMENT SPECIFICATION (URS)

6.1

Objective

6.2

Reason for URS

6.3

Requirements

6.4

Attachments

6.5

Recommendations/ Conclusion

6.6

Post approval

7.0

DESIGN QUALIFICATION (DQ)

7.1

Objective

7.2

Reason for DQ

7.3

Requirements

7.4

Attachments

7.5

Expected Documents and Drawings

7.6

Recommendations/ Conclusion

7.7

Post approval

8.0

INSTALLATION QUALIFICATION (IQ)

8.1

Objective

8.2

Reason for IQ

8.3

Requirements

8.4

Attachments

8.5

Expected Documents and Drawings

8.6

Deviations/ Changes (if any)

8.7

Recommendations/ Conclusion

8.8

Post approval

9.0

OPERATION QUALIFICATION (OQ)

9.1

Objective

9.2

Reason for OQ

9.3

Training

9.4

Verification of instruments for calibration status

9.5

Reference of Standard operating procedure (SOP)

9.6

Operational Requirements

9.7

Attachments

9.8

Deviations/Incident/Changes (if any)

9.9

Recommendations/Conclusion

9.10

Post approval

10.0

PERFORMANCE QUALIFICATION (PQ)

10.1

Objective

10.2

Reason for PQ

10.3

Training

10.4

Verification of instruments for calibration status

10.5

Performance Requirements

10.6

Attachments

10.7

Deviations/Incident/Changes/OOS (if any)

10.8

Recommendations/Conclusion

10.9

Post approval


1. Pre-approval Protocol
This document has been developed and the individuals listed below have reviewed the document and agree with its content and with their signature grant approval for its execution.

Functional area

Name

Designation

Signature

Date

PREPARED BY

Validation QA

 

 

 

 

CHECKED BY

Quality Assurance

 

 

 

 

REVIEWED BY

Production Head

 

 

 

 

Warehouse Head

 

 

 

 

Environment, health and safety

 

 

 

 

Quality Control Head

 

 

 

 

Engineering Head

 

 

 

 

APPROVED BY

QA Head

 

 

 

 

Plant Head

 

 

 

 


2. Objective
To ensure that the critical attributes of the pharmaceutical manufacturing, packaging, storage and Microbiological testing Facility/area are designed, installed and functioning as per the designed specification throughout the anticipated operating ranges and meets the cGMP requirements and regulations.

3. Scope
The scope of this Facility Qualification is that the Receipt, Storage, dispensing, sampling, manufacturing, packaging, Microbiological testing and ancillary areas such as change rooms, corridors etc. are constructed according to specified design/required standards and regulation.

4. Reason for Qualification
The reason for preparing this document is: Please tick any one (or multiple) option(s) from the following (✅):

New or refurbished area

Major change in area/HVAC design

 

 

Change in AHU/ AHU parameters

 

 

Addition or removal of major equipment resulting in civil work Equipment replacement of different capacity

 

 

 

Periodic Re-qualification

Others (Specify)

 

 

 



5. Responsibility
Personnel involved in qualification activity.

Department

Name

Activity

 

User Department

 

To prepare the document as per the user Requirement and Design of area based on Process/Product, cGMP and Regulatory guidelines.

 

User Dept. Head

 

To verify and document all the critical aspects of Requirement and Design of area based on Process/Product, cGMP and Regulatory guidelines.

 

Engineering

 

 

To verify the Engineering and safety aspects of the Area

 

Environment, Health and Safety

 

 

To verify the Safety and Environment aspects of the Area

Quality Assurance

 

To be a part of team and review the documents

 

QA Head

 

To review and approve the requirement and Qualification document

 

Plant Head

 

To review and approve the requirement and Qualification document


6. User Requirement Specification (URS)

6.1 Objective: 
The objective of URS is to provide the requirement and appropriate design to identify company needs and performance requirements of area including major ancillary component or fabrication of the area so as to meet the in-house requirements as well as compliance with cGMP.

6.2 Reason for URS:
To provide the requirements for Designing and installation of facility or area in ______ block for manufacturing, packaging, storage and Microbiological testing of pharmaceutical products.

6.3 Requirements:
All the requirements are mentioned area wise as per respective attachments as listed in below table.

Refer Annexure No.

Area Code

Area Name

FQ/URS/B1/Annex-1

 

 

FQ/URS/B1/Annex-2

 

 

FQ/URS/B1/Annex-3

 

 

FQ/URS/B1/Annex-4

 

 

FQ/URS/B1/Annex-5

 

 


6.4 Attachments:
This section contains a list of all additional attachments which are required to be attached.

Sr. No.

Attachment Details

Refer Attachment No.

1.

 

FQ/URS/B1/Attachment-1

2.

 

FQ/URS/B1/Attachment-2

3.

 

FQ/URS/B1/Attachment-3


6.5 Recommendations/Conclusion:
...................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................

6.6 Post approval:
This document has been developed and the individuals listed below have reviewed the document and agree with its content and with their signature grant approval for its execution.

Functional area

Name

Designation

Signature

Date

REVIEWED BY

Production Head

 

 

 

 

Warehouse Head

 

 

 

 

EHS

 

 

 

 

Engineering Head

 

 

 

 

Quality Control Head

 

 

 

 

Quality Assurance

 

 

 

 

APPROVED BY

QA Head

 

 

 

 

Plant Head

 

 

 

 



7. Design Qualification (DQ):

7.1 Objective: 
To prepare the detailed specification (Design data) of area to ensure that the user requirement specification and Functional requirement specification or data sheet are achieved.

To design the area in conjunction with the design data in order to provide basis for the vendor, manufacturer, contractor and design engineer for designing the area when the project begins.


7.2 Reason for DQ:
To provide a design for installation of facility or area in block for production of pharmaceutical products.

7.3 Requirements:
All the requirements are mentioned area wise as per respective attachments as listed in below table.

Refer Annexure No.

Area Code

Area Name

FQ/DQ/B1/Annex-1

 

 

FQ/DQ/B1/Annex-2

 

 

FQ/DQ/B1/Annex-3

 

 

FQ/DQ/B1/Annex-4

 

 

FQ/DQ/B1/Annex-5

 

 


7.4 Attachments:
This section contains a list of all additional attachments which are required to be attached.

Sr. No.

Attachment Details

Refer Attachment No.

1.

 

FQ/DQ/B1/Attachment-1

2.

 

FQ/DQ/B1/Attachment-2

3.

 

FQ/DQ/B1/Attachment-3


7.5 Expected Documents and Drawings:
A suggestive list (but not limited to), is as listed below:

Sr. No.

Document details

Required

1.

Design Specifications

 

2.

Functional Specifications

 

3.

As Built Area Layout

 

4.

Instrument Listing

 


Sr. No.

Document details

Required

1.

Utility supply Piping and Instrumentation Diagram

 

2.

MOC certificates

 

3.

Test certificates of components/ instruments

 

4.

Weld certificates (if any)

 

5.

Electrical drawings

 

6.

Other (Specify)

 


✅ : Applicable & required                            × : Not applicable

7.6 Recommendations/Conclusion:
...................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................

7.7 Post approval:
This document has been developed and the individuals listed below have reviewed the document and agree with its content and with their signature grant approval for its execution.

Functional area

Name

Designation

Signature

Date

REVIEWED BY

Production Head

 

 

 

 

Warehouse Head

 

 

 

 

EHS

 

 

 

 

Engineering Head

 

 

 

 

Quality Control Head

 

 

 

 

Quality Assurance

 

 

 

 

APPROVED BY

QA Head

 

 

 

 

Plant Head

 

 

 

 



8. Installation Qualification (IQ):

8.1 Objective:
To ensure that all the critical attributes of area have been taken care and to establish that the area is constructed as per the approved design specification.

8.2 Reason for IQ:
To verify the installation parameters of facility based on approved Design of facility or area in block for production of pharmaceutical formulation.

8.3 Requirements:
All the requirements are mentioned area wise as per respective attachments as listed in below table.

Refer Annexure No.

Area Code

Area Name

FQ/IQ/B1/Annex-1

 

 

FQ/IQ/B1/Annex-2

 

 

FQ/IQ/B1/Annex-3

 

 

FQ/IQ/B1/Annex-4

 

 

FQ/IQ/B1/Annex-5

 

 


8.4 Attachments:
This section contains a list of all additional attachments which are required to be attached.

Sr. No.

Attachment Details

Refer Attachment No.

1.

 

FQ/IQ/B1/Attachment-1

2.

 

FQ/IQ/B1/Attachment-2

3.

 

FQ/IQ/B1/Attachment-3



8.5 Expected Documents and Drawings:
A suggestive list (but not limited to), is as listed below:

Sr. No.

Document details

Required

1.

Design Specifications

 

2.

Functional Specifications

 

3.

As Built Area Layout

 

4.

Instrument Listing

 

5.

Utility supply Piping and Instrumentation Diagram

 

6.

MOC certificates

 

7.

Test certificates of components/ instruments

 

8.

Weld certificates (if any)

 

9.

Electrical drawings

 

10.

Other (Specify)

 

✅ : Applicable & required                            × : Not applicable

8.6 Recommendations/Conclusion:
...................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................

8.7 Post approval:
This document has been developed and the individuals listed below have reviewed the document and agree with its content and with their signature grant approval for its execution.

Functional area

Name

Designation

Signature

Date

REVIEWED BY

Production Head

 

 

 

 

Warehouse Head

 

 

 

 

EHS

 

 

 

 

Engineering Head

 

 

 

 

Quality Control Head

 

 

 

 

Quality Assurance

 

 

 

 

APPROVED BY

QA Head

 

 

 

 

Plant Head

 

 

 

 



9. Operational Qualification (OQ):

9.1 Objective: 
To ensure that the critical attributes of the area are functioning as per the operational specification throughout the anticipated operating ranges.

9.2 Reason for OQ:
To verify the operating parameters of facility based on the approved Design of facility or area in block for production of pharmaceutical formulation.

9.3 Training:
Personnel involved in qualification activity.

Sr. No.

Name

Training status

Training report availability

Checked by/ date

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


9.4 Verification of instruments for calibration status:

Sr. No.

Instrument Name

Instrument ID

Calibration done on

Calibration due on

Checked by Sign/ Date

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


9.5 Reference of Standard operating procedure (SOP):

Sr. No.

SOP Name

SOP No.

Checked by

Sign/ Date

 

 

 

 

 

 

 

 

 

 

 

 


9.6 Operational Requirements:
All the requirements are mentioned area wise as per respective attachments as listed in below table.

Refer Annexure No.

Area Code

Area Name

FQ/OQ/B1/Annex-1

 

 

FQ/OQ/B1/Annex-2

 

 

FQ/OQ/B1/Annex-3

 

 

FQ/OQ/B1/Annex-4

 

 


9.7 Attachments: 
This section contains a list of all additional attachments which are required to be attached.

Sr. No.

Attachment Details

Refer Attachment No.

1.

 

FQ/OQ/B1/Attachment-1

2.

 

FQ/OQ/B1/Attachment-2

3.

 

FQ/OQ/B1/Attachment-3


9.8 Deviations/ Incident/ Changes (if any):
...................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................

9.9 Recommendations/ Conclusion:
...................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................

9.10 Post approval:
This document has been developed and the individuals listed below have reviewed the document and agree with its content and with their signature grant approval for its execution.

Functional area

Name

Designation

Signature

Date

REVIEWED BY

Production Head

 

 

 

 

Warehouse Head

 

 

 

 

EHS

 

 

 

 

Engineering Head

 

 

 

 

Quality Control Head

 

 

 

 

Quality Assurance

 

 

 

 

APPROVED BY

QA Head

 

 

 

 

Plant Head

 

 

 

 



10. Performance Qualification (PQ):

10.1 Objective:
To confirm that the area/facility consistently meets the predetermined standards under normal and worst conditions.

10.2 Reason for PQ:
To verify the performance of facility based on the approved Design, process, product and regulatory requirements of facility or area in block for production of pharmaceutical formulation.

10.3 Training:
Personnel involved in qualification activity.

Sr. No.

Name

Training status

Training report availability

Checked by/ date

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


10.4 Verification of instruments for calibration status:

Sr. No.

Instrument Name

Instrument ID

Calibration done on

Calibration due on

Checked by Sign/ Date

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


10.5 Performance Requirements: 
All the requirements are mentioned area wise as per respective attachments as listed in below table.

Refer Annexure No.

Area Code

Area Name

FQ/PQ/B1/Annex-1

 

 

FQ/PQ/B1/Annex-2

 

 

FQ/PQ/B1/Annex-3

 

 

FQ/PQ/B1/Annex-4

 

 


10.6 Attachments:
This section contains a list of all additional attachments which are required to be attached.

Sr. No.

Attachment Details

Refer Attachment No.

1.

 

FQ/PQ/B1Attachment-1

2.

 

FQ/PQ/B1Attachment-2

3.

 

FQ/PQ/B1Attachment-3

4.

 

FQ/PQ/B1Attachment-4

5.

 

FQ/PQ/B1Attachment-5


10.7 Deviations/ Incident/ Changes/ OOS (if any):
……………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………….........................

10.8 Recommendations/ Conclusion:
……………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………….........................

10.9 Post approval:
This document has been developed and the individuals listed below have reviewed the document and agree with its content and with their signature grant approval for its execution.

Functional area

Name

Designation

Signature

Date

REVIEWED BY

Production Head

 

 

 

 

Warehouse Head

 

 

 

 

EHS

 

 

 

 

Engineering Head

 

 

 

 

Quality Control Head

 

 

 

 

Quality Assurance

 

 

 

 

APPROVED BY

QA Head

 

 

 

 

Plant Head

 

 

 

 


Post a Comment

Previous Post Next Post
close