- Objective
- Instrument Description & Identification
- Installation Check List
- Major Components
- Utilities
- Standard Operating Procedure / Calibration Procedure
- Installation Verification
- Summary of Installation Qualification
- Qualification of the unit installation and examination of all background information are performed to ensure conformance to PharmaGuide Limited and manufacturer specifications.
- The Instrument meets the current regulatory requirements.
- No unauthorized or unrecorded modifications have taken place.
- Standard Operating Procedures (SOP), Calibration Procedures and
- All critical instrumentation has been identified.
- All utilities are properly connected.
- All test reports, drawings, and manuals, are available and maintained
- The UV-1800 is a compact, double-beam UV-VIS spectrophotometer wrapped in a sleek form-fitting case.
- The UV-1800 uses a Czerny-Turner monochromator which provides for a bright optical system, in a compact design.
- The UV-1800 can be operated as a stand-alone system or with UV Probe software.
- The UV-1800 is USB-memory ready, which enables users to save measurement data to USB memory for data analysis and printing on a PC.
- Sophisticated and easy-to-use UVProbe PC software comes standard and makes data processing easy. Offering Spectrum, Photometric, Quantitation, Kinetics, Time Course, and Bioapplication modes, the UV-1800 is equipped to handle all of your laboratory needs.
- With an array of user-friendly features, the UV-1800 easily satisfies pharmacopeia requirements and the demands of university laboratories, government agencies, and the food industry.
| Manufacturer: |   | 
| Instrument Name: |   | 
| Instrument ID: |   | 
| Model Number: |   | 
| Serial No.:                            |   | 
| Sr. No | Item | 
| 1 | Instrument appearance check | 
| 2 | Parts Check | 
| 3 | Installation site check | 
| Sr. No | Item | Observation | Checked by | |
| 1 | Instrument appearance check | 
 | 
 | |
| 2 | Part Check | Part No | Observation | Checked by | 
| 2.1 | Basic unit | 
 | 
 | 
 | 
| 2.2 | AC power cable | 
 | 
 | 
 | 
| 2.3 | Instruction manual, operation guide | 
 | 
 | 
 | 
| 2.4 | Instruction manual, system user guide | 
 | 
 | 
 | 
| 2.5 | UV-1800 Inspection certificate | 
 | 
 | 
 | 
| 2.6 | UV-Probe CD ROM | 
 | 
 | 
 | 
| 2.7 | UV Probe tutorial | 
 | 
 | 
 | 
| 2.8 | UV Probe software release note | 
 | 
 | 
 | 
| 2.9 | UV Probe software release note | 
 | 
 | 
 | 
| 2.10 | Shimadzu user authentication Tool instruction manual | 
 | 
 | 
 | 
| 2.11 | Software agreement license | 
 | 
 | 
 | 
| 3 | Installation site Check | |||
| 3.1 | Dry and indoors | 
 | 
 | |
| 3.2 | Away from draughty or hot equipment like fans or heater | 
 | 
 | |
| 3.3 | Within reach of PowerPoint | 
 | 
 | |
| 3.4 | Away from potential sources of interference, such as RFI-generating equipment | 
 | 
 | |
| 3.5 | Not to use a power circuit that also has large motors | 
 | 
 | |
| 3.6 | Away from direct sunlight | 
 | 
 | |
| Description | Specified | Checked By | 
| Make | 
 | 
 | 
| Model No. | 
 | 
 | 
| Sr. No. | 
 | 
 | 
| Dimensions | 
 | 
 | 
| Light Source | 
 | 
 | 
| Installation Consideration | Yes/No | 
 | 
| Properly mounted, supported & connected | Yes/No | 
 | 
| Properly labeled / Identified | Yes/No | 
 | 
| Voltage | 110 - 230V | 
| Frequency | 50 - 60 Hz | 
| Maximum Current | 200 mA | 
6. SOP / CALIBRATION PROCEDURES
Identify and list the Standard Operating Procedures / Calibration Procedures
| Title | Number | Checked By | 
| Operation and calibration procedure of UV SPECTROPHOTOMETER | 
 | 
 | 
| Sr. No | Consideration | Yes/No | Checked By | 
| 1. | Major components are securely anchored and protected from shock | 
 | 
 | 
| 2. | There is no observable physical damage | 
 | 
 | 
| 3. | Sufficient room for servicing provided | 
 | 
 | 
| 4. | Required electrical connections are tight and weather proofed and grounded | 
 | 
 | 
| 5. | Instrument identification nameplate is visible | 
 | 
 | 
| 6. | Unit installed and secured in place as per manufacturer recommendations | 
 | 
 | 
| Sr. No | Description | Yes/No | Checked By | 
| 1. | All acceptance criteria set forth in the Installation Qualification was met | 
 | 
 | 
| 2. | All specifications verified | 
 | 
 | 
| 3. | Deviations if any | 
 | 
 | 
| 
 | Signatories | Signature | Date | 
| Executed by | Quality control | 
 | 
 | 
| Reviewed by | Quality control | 
 | 
 | 
| Approved by | QA Manager | 
 | 
 | 