OBJECTIVE
To verify that the machine at the manufacturer’s site is ready as per the design qualifications and in line with all the technical specifications laid down in the user requirement specification.
SCOPE
The scope of this document is limited to the Factory Acceptance Test of Inspection Conveyor
RESPONSIBILITIES
Manufacturer:
The manufacturer is responsible for the preparation of the FAT protocol, unless and until it is specified by the customer for its indigenous protocol.
The manufacturer shall assist the customer in performing the Factory Acceptance Test at the manufacturer’s factory, unless it is specified by the customer to conduct the PROXY-FAT.
Customer:
The customer shall conduct the factory acceptance test at the manufacturer’s factory.
In case the customer wants the manufacturer to conduct the PROXY-FAT, a written communication, as an ANNEXURE, shall be attached along with this protocol.
VERIFICATION OF TECHNICAL SPECIFICATION
|
Sr. No. |
Parameter |
Specifications |
|
1 |
Model |
PVBI-120 |
|
2 |
Main
Motor |
Make: Bonfiglioli Rating: 0.25 HP / 0.18 kW / 1.01 A / 230 V / 1360
RPM / 3 Phase Serial No.: 210380522292 |
|
3 |
Main Gear
Box |
Make:
Bonfiglioli Model:
VF44 F120 P63 B5B3 Ratio:
20:01 Serial
No.: 09 B03202500180 |
|
4 |
Main
A.C. Drive |
Make: Allen Bradley Model: 22F-A2P5N103 Rating: 0.5 HP / 2.5 A / 230 V Serial No.: FA2P5NOW21030279 |
|
5 |
Main Switch |
Make:
Schneider |
|
6 |
Machine
Dimension |
1520 mm (L) × 850 mm (W) × 1550 mm (H) |
VERIFICATION OF MATERIAL OF CONSTRUCTION
|
Component |
MOC (Material of Construction) |
|
Machine
Frame Structure |
SS Square
Pipe Frame |
|
Conveyor |
SS
304 |
|
Sprocket |
Nylon |
VERIFICATION OF INSTRUMENT
Potentiometer
Make: POT KNOB
VERIFICATION OF OPERATION
Method of Simulation: Function
Main Power ON/OFF switch: To supply power to the unit with Green indication ‘ON’.
Potentiometer: For the speed variation
MACHINE TRIAL SHEET
- Machine trail in empty run
- Abnormal Sound
FAT CLOSE OUT
- The Factory Acceptance Test for the turntable stands completed.
- All the parameters have been checked and found in line with the requirement
- The machine is cleared by the undersigned authority.
ALSO READ: Preventive Maintenance Checklist for HVAC